The Kentucky General Assembly approved the Livingston County project in 2005 and authorized its funding in 2006. The total project cost was $8.9 million for 28,950 square feet and was completed in January 2009.
JRA Architects of Louisville designed the Livingston County Justice Center. B.H. Green & Son of Paducah was the general contractor and Hilliard Lyons of Louisville was the financial agent.
Project Development Board
Chris Lasher, County Judge Executive
Terry Stringer, Fiscal Court Representative
C.A. Woodall III, Livingston County Circuit Judge
Debbie Knoth, Livingston County Circuit Clerk
Raymond McGee, Kentucky Bar Association Representative
Phyllis Teeters, AOC Representative
Ivus Crouch and Jackie Doom, Former Board Members
Brad Smith, AOC Division of Capital Construction
Project Completion Team
General Contractor, B.H. Green & Son, Paducah, KY
Architect, JRA Architects, Louisville, KY
Financial Advisor, Hilliard Lyons, Louisville, KY
Bond Counsel, Rubin & Hays